Green Lake, December 2024: Significant Progress and Visions for the Future
The Green Lake residential project, located on the shores of Lake Grivița in northern Bucharest, continues to make significant progress. With the first villas nearing completion and work well underway on the apartments and infrastructure, the Green Lake community is becoming a reality. Discover the latest updates on construction progress, delivery dates, and plans for the future.
Lot G: The First Villas to Be Completed in December 2024
In Lot G, construction on the first five villas is nearing completion. By the end of December 2024, these modern, well-designed villas will be ready to welcome their new owners. Lot G thus becomes the first fully completed area in Green Lake, marking an important milestone in the development of the entire project.
In addition, the road infrastructure around Lot G will also be completed this month, providing easy access and seamless connectivity with the rest of the neighborhood.
Visit the Villa Showroom in Lot G
Starting in January 2025, the showroom villa in Lot G will be fully completed and open for tours. It offers a unique opportunity to see the premium finishes, smart layouts, and modern design that define Green Lake homes. Schedule a visit and discover why Green Lake is the perfect choice for an exclusive lifestyle.
Lot C: Major Progress and Expansion Plans
In Lot C, construction on the first row of six villas is nearly complete. The structural work is finished, and the delivery date for these villas is set for early September 2025.
In addition to this row, construction of the second row of seven villas will begin in 2025. Once completed, all 13 villas in Lot C will mark the completion of construction for this lot, which is fully integrated into the Green Lake community and offers modern, well-located homes.
Lot B: Modern Apartments Completed Ahead of Schedule
Progress continues in Lot B as well, where the structural work on the two buildings was recently completed, and masonry work has begun. These buildings, which include a total of 56 apartments, are scheduled for delivery in September 2025.
As of today, there are still 16 apartments available for sale, each designed to offer comfort and functionality. The roads serving Lot B will be completed at the same time, ensuring easy access for the new owners.
Lot F: Construction of the First Series of Villas
In Lot F, construction of the first series of seven villas is underway. This phase includes:
- 2 Type A villas and 2 Type C villas, both designed to combine optimized living spaces with private gardens;
- 3 Type D villas, each completely independent, offering a high level of privacy and luxury.
These villas will be delivered in September 2025, and construction on the next series of 10 villas is scheduled to begin in 2025. Once completed, Lot F will add new, modern housing options to Green Lake.
Road Infrastructure Completed for Sections F, C, and B
Another key aspect of the project is the road infrastructure, which is progressing in all areas of the community. The roads serving Lots F, C, and B will be fully completed by September 2025, ensuring efficient connectivity between all Green Lake lots and quick access to major transportation routes.