Update on Construction and Superstructure Work on Lot B at Green Lake

Construction of the apartment buildings on Lot B of the Green Lake residential project is moving along at a brisk pace, demonstrating the remarkable progress made in less than five months since the project began. To keep you informed, here are the latest details regarding the construction progress.

Infrastructure Nearing Completion
Infrastructure work for the apartment buildings is 98% complete. The only remaining elements are the foundations for the vehicle ramp and the access roads, which will be completed in the first half of next year.

Important Structural Stages in Building Construction

  • Building C1A: The superstructure has reached a major milestone, with the floor slab above the first floor already poured.
  • Building C1B: Work is currently underway on reinforcing the floor slab above the first floor, while the vertical structural elements on the first floor of C1A have already been reinforced.
  • Building C2: The vertical structural elements of the second floor have been completed, and the staircases, made of prefabricated components, are currently being installed.

As always, we strive to maintain steady progress while adhering to the highest standards of quality and safety. Stay tuned for more updates on this special project as we continue to build the future of Green Lake.